| ac | Actual Cost (AC). |
| building_project | Mid-Rise Commercial Building Construction Project |
| contingency | Contingency Calculation. |
| cor_matrix | Generate Correlation Matrix from Random Samples. |
| cost_pdf | Cost Probability Density. |
| cost_post_pdf | Posterior Cost Probability Density. |
| cpi | Cost Performance Index (CPI). |
| cv | Cost Variance (CV). |
| eac | Estimate at Completion (EAC). |
| etc | Estimate to Complete (ETC). |
| ev | Earned Value (EV). |
| fit_sigmoidal | Fit a Sigmoidal Model to Data. |
| grandparent_dsm | Risk-based 'Grandparent' Design Structure Matrix (DSM). |
| mcs | Monte Carlo Simulation. |
| parent_dsm | Resource-based 'Parent' Design Structure Matrix (DSM). |
| plot.dsm | Plot a DSM heatmap. |
| plot_sigmoidal | Plot a Fitted Sigmoidal Model. |
| pra_mcp_server | Start a PRA MCP Server |
| pra_tools | Create PRA Tool Definitions for LLM Agent |
| predict_sigmoidal | Predict a Sigmoidal Function Using Fitted Model. |
| print.dsm | Print a DSM object. |
| print.mcs | Print method for Monte Carlo Simulation results. |
| print.pra_sigmoidal_fit | Print method for Sigmoidal Model |
| print.smm | Print method for SMM results. |
| prob_net | Probabilistic Network of Project Risks. |
| prob_net_learn | Perform Bayesian Learning on a Probabilistic Network of Project Risks. |
| prob_net_sim | Perform Inference on a Probabilistic Network of Project Risks. |
| prob_net_update | Update a Probabilistic Network of Project Risks. |
| pv | Planned Value (PV). |
| risk_post_prob | Posterior Risk Probability. |
| risk_prob | Bayesian Inference for Risk Probability. |
| sensitivity | Sensitivity Analysis. |
| smm | Second Moment Method Analysis. |
| spi | Schedule Performance Index (SPI). |
| sv | Schedule Variance (SV). |
| tcpi | To-Complete Performance Index (TCPI). |
| vac | Variance at Completion (VAC). |