criticalpath Package

criticalpath package is an R implementation of the Critical Path Method (CPM) in R with R6 library. CPM is a method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model. The flexibility is in terms of early start, early finish, late start, late finish, total float and free float. Beside, it permits to quantify the complexity of network diagram through the analysis of topological indicators. Finally, it permits to change the activities duration to perform what-if scenario analysis.

With this package, you can calculate the following CPM parameters:

The aim of this package is to apply critical path method, for Project Manager and Researches make “What if?” scenario analysis or experiments with CPM parameters.

Installation

You can install the released version of criticalpath from CRAN with:

#install.packages("criticalpath")

Example

To create a schedule:

library(criticalpath)

sch <- sch_new() %>% 
  sch_title("Project 1: Cost Information System") %>% 
  sch_reference("VANHOUCKE, Mario.
Integrated project management and control:
  first comes the theory, then the practice.
  Gent: Springer, 2014, p. 6") %>% 
  sch_add_activities(
    id        = 1:17,
    name      = paste("a", as.character(1:17), sep=""),
    duration  = c(1L,2L,2L,4L,3L,3L,3L,2L,1L,1L,2L,1L,1L,1L,1L,2L,1L)
  ) %>% 
  sch_add_relations(
    from = c(1L, 1L, 2L, 2L, 2L, 3L, 3L, 3L,  3L,  4L,  5L,  6L,
           7L,  8L,  9L, 10L, 11L, 11L, 12L, 12L, 13L, 13L, 14L, 14L, 15L, 15L),
    to   = c(2L, 3L, 4L, 5L, 6L, 7L, 8L, 9L, 10L, 11L, 11L, 11L,
           12L, 13L, 14L, 15L, 16L, 17L, 16L, 17L, 16L, 17L, 16L, 17L, 16L, 17L)
  ) %>% 
  sch_plan()

What is the schedule duration?

sch_duration(sch)
#> [1] 11

Which activities are critical?

sch_critical_activities(sch)
#> # A tibble: 5 x 14
#>      id name  duration milestone critical early_start early_finish late_start
#>   <int> <chr>    <int> <lgl>     <lgl>          <int>        <int>      <int>
#> 1     1 a1           1 FALSE     TRUE               0            1          0
#> 2     2 a2           2 FALSE     TRUE               1            3          1
#> 3     4 a4           4 FALSE     TRUE               3            7          3
#> 4    11 a11          2 FALSE     TRUE               7            9          7
#> 5    16 a16          2 FALSE     TRUE               9           11          9
#> # ... with 6 more variables: late_finish <int>, total_float <int>,
#> #   free_float <int>, progr_level <int>, regr_level <int>, topo_float <int>

What is the critical relations?

sch_critical_relations(sch)
#> # A tibble: 4 x 8
#>    from    to type    lag critical   ord i_from  i_to
#>   <int> <int> <chr> <int> <lgl>    <int>  <int> <int>
#> 1     1     2 FS        0 TRUE         1      1     2
#> 2     2     4 FS        0 TRUE         3      2     4
#> 3     4    11 FS        0 TRUE        10      4    11
#> 4    11    16 FS        0 TRUE        17     11    16

More information

CRAN - Package criticalpath

criticalpath Page

These binaries (installable software) and packages are in development.
They may not be fully stable and should be used with caution. We make no claims about them.